Building four additional levels on top of an existing multi-level car park means the structure below has to be capable of carrying them. The $40m+ Bogong Avenue extension in Glen Waverley added four floors and 522 spaces, taking the car park to 1,037 — and none of it could proceed until the existing footings were reinforced to take the load.
Austral Contractors was engaged by LB Concrete Solutions to deliver the early works.
We core drilled and installed more than 12,000 starter bars into the existing footings, each hole drilled to line and depth, cleaned, epoxied and dowelled to tie the new structure into the old. At that volume, the job is one of consistency: every hole to the same specification, every bar to the same embedment, sustained across thousands of repetitions without a drop in standard. Get one wrong and it is buried in the pour.
Alongside the drilling and doweling we carried out road sawing, rock drilling and robotic demolition as required to open up and prepare the structure for the extension works.
Early works of this kind rarely get photographed and never appear in the renders. But the four new levels sitting above Bogong Avenue today are carried by 12,000 bars that had to be right the first time.
The extension opened in April 2025 and includes new lifts, EV charging bays, smart parking wayfinding and a rooftop solar system.
- Client: LB Concrete Solutions
- Industry: Building Construction