Inland Rail is upgrading 262km of existing line between Beveridge and Albury so double-stacked freight trains can run the Melbourne–Brisbane corridor. At the Hume Freeway bridge in Tallarook, that means realigning the track and lowering it by around two metres at the lowest point beneath the bridge, with modifications to the existing pier and abutments.
Lowering a rail corridor beneath a live freeway bridge means cutting into the structure holding the ground back on either side.
Austral Contractors was engaged by John Holland to demolish the soil nail walls across multiple abutment elevations, delivered in five stages.
The sequence was the same on every elevation, and it was designed to keep control at every point:
- Horizontal wall saw separation cuts to isolate each section from the structure above and below
- Vertical ring saw keyway cuts to create defined breakout zones, giving the demolition somewhere to start and, more importantly, somewhere to stop
- Low-vibration robotic demolition to remove the concrete within those zones
The order matters. Cutting the boundaries before breaking anything meant every section came away along a line we had already established, rather than propagating into concrete that had to stay. Robotic demolition kept the operator away from the face and off the wall, working remotely at a controlled rate, with vibration held low enough not to disturb retained ground, the adjacent bridge structure or a rail corridor that remained in service around us.
- Client: John Holland
- Industry: Rail
We Work With